Table of Contents(Page UD-63)

Ultra-DekŪ DESIGN

FLOATING PEAK BOX INSTALLATION

  1. Install rake trim on each side of ridge to within 2" of centerline of building.
  2. Install ridge flash so that it is on top leg of rake trim, 1" back from outside edge.
  3. Temporarily set peak box in place and mark perimeter of box on rake trim and ridge flash. Remove peak box.
  4. Just inside mark, install tape sealer continuously across ridge flash, then down the face of rake trim on both sides of ridge.
  5. Place flexible membrane over tape sealer and hold in place with cinch angles. Cinch angles should be attached with Fastener #4. To prevent leaks, flexible membrane should be tight against ridge flash and rake trim with no wrinkles at the sealed edges.
  6. Hook top of peak box over cinch angles installed on top of ridge flash and attach bottom of peak box to endwall with Fastener #4.