SUBSEQUENT RUNS EAVE
Apply tape sealer to the male leg of the
first panel run directly over the inside closure. This will prevent water
infiltration through the end of the seam. Install the next run of
insulation and another inside closure using Fastener #1. The second run of
roof is now ready to install.
Position the panel with the female lip
resting on top of the male leg. Align panel flush with adjacent panel.
ONCE THE PANELS ARE SNAPPED TOGETHER, NO FURTHER ALIGNMENTS CAN BE MADE.
Press down on the seam, snapping the two panels together. It is important
to begin at one end of the panel and work to the other, applying pressure
continuously all the way along the seam to avoid a bubble in the seam.
Make certain the seams are fully locked together, particularly at the
clips where greater resistance will be encountered.
Install fasteners at eave in the proper
sequence. Eight fasteners are required at this location.
 |
CAUTION
Never use a hammer to force the panels to snap together. This will
cause severe damage to the panel and will nullify any warranty. |
 |
CAUTION
If a problem is encountered in fully snapping the seams together,
such as an incorrectly installed clip, damaged pane’ lip, or a
bubble caused by faulty assembly: the shaping tool should enable
the seam to be locked with minimal effort |
|