Install eave trim to structure with three pop rivets per section.
Install inside closures along top leg of eave trim with 1/2" x
3/32" tape sealer top and bottom.
Install "PBR", "PBU" or S-36® panel with
Fastener #3 (12-14 x 1 1/4"
Long Life driller) on each side of major ribs (2 fasteners per foot)
allowing panel to overhang 1 1/2" plus wall thickness. Fasteners must be installed up slope
from inside closures.
Attach front face of eave trim to wall with fasteners or cleat as required
for wall substrate.
Trim laps should overlap approximately 3" with a bead of urethane
sealant in between. Install a sufficient amount of Fastener #14 pop rivets to hold lap
together.