| Table of Contents(Page DL-31) |
Double-LokŪ ERECTION SEQUENCE
Step 2B
|
|
|
||
|
HIGH SYSTEM EAVE Install high eave plates flush with the outside of the high crowns of the wall panels. Install Fastener #1 in prepunched slot (1'-0" on center) of the eave plate. The first eave plate will butt against the rake support. You may install all of the eave plates at this time. Install box panel cap trim to the top of the eave plates with Fastener #14. Use two fasteners per 10' piece and three fasteners per 20' piece. Trim must be pulled tight to wall panels before fastening to eave plates. Lay Tri-Bead tape sealer across the top of the box panel cap trim, flush with the outside edge. Install double faced tape along the length of the top leg of the box panel cap trim. Double faced tape must be upslope from the Tri-Bead tape sealer. Wall Panels Installed After Roof Install offset panel cap trim to eave strut with Fastener #14. Use two fasteners per 10' piece and three fasteners per 20' piece. Install high eave plates flush with the outside of the offset panel cap trim. Install Fastener # 1 in each prepunched slot (1'-0" on center) of the eave plate. The first eave plate will butt against the rake support. You may install all of the eave plates at this time. Lay Tri-Bead tape sealer across the top of the eave plates, flush with the outside edge. Install double faced tape along the length of the bottom leg of the eave plate. TRIM LAPS Lap box or offset panel cap trim 3". Apply two beads of urethane sealant between the trim pieces, approximately 2 1/2" from the end of the bottom piece. |